Rehabilitation and modernization of sirhind feeder
The Sirhind Feeder is a critical component of Punjab’s irrigation system, and its rehabilitation was a priority for the state government. Our involvement in this 100-kilometer modernization project focused on a 3-kilometer segment with a budget of ₹20 crores. The task had to be completed within a tight 25-day deadline, and the aim was to significantly improve water flow efficiency while modernizing aging infrastructure. This project was crucial to sustaining agricultural productivity in Punjab, where the canal system plays a vital role.
The Challenge Was
This project presented multiple challenges, including completing the rehabilitation of a key segment of the Sirhind Feeder within a very short period. The tight timeline and the importance of the feeder for local agriculture increased the project’s complexity.
- Rehabilitating 3 kilometers of canal infrastructure
- Working under a strict 25-day deadline
- Managing a budget of ₹20 crores while ensuring quality
Our Solution Was
Our team rose to the challenge by leveraging modern technology and efficient project management techniques to deliver the project on time. We worked in shifts around the clock to ensure that the project was completed to the client’s satisfaction.
- Completed the 3-kilometer segment in 25 days
- Enhanced water flow efficiency through modernization
- Delivered high-quality work within the assigned budget